Bulgarian energy regulator: Gas interconnector with Greece will not be ready until June 2022

Ivan Ivanov
Photo: BGNES

The Gas Interconnector Greece-Bulgaria through which gas should be delivered from Azerbaijan, will not be ready by the middle of 2022, said the chairman of the Bulgarian Energy and Water Regulatory Commission, Ivan Ivanov.

"We agreed on the request received from the company ICGB for extension of the term for commissioning of the interconnector from Greece's Komotini to Bulgaria's Stara Zagora until June 30, 2022. This is the foreseeable period during which the interconnector Nea Mesimvria - Siderokastro - Kulata will have to be used for alternative deliveries. And they are absolutely necessary for Bulgaria, because they can have a positive impact on consumers regarding the price of natural gas". 



The capacity for deliveries on the current interconnector is reserved only until September, Ivanov warned.

More from category

Sofia absorbs almost one third of EU funds for the country

Bulgaria has used over 7 billion euros from the EU budget. T his has been the total amount of money under the various EU funds since Bulgaria joined the community. Dobrich, Svilengrad, Kostinbrod, Primorsko, Byala and Sozopol..

published on 7/30/21 12:37 PM

Bulgarian exports have gone up by 20% over past 5 years

In 2020 Bulgaria exported commodities worth USD 31.8 billion, a drop of 4.4% compared to the pre-pandemic 2019 when exports amounted to USD 33.4 billion.   Bulgaria climbs to 58 th from 60 th position in 2019 among all exporters globally...

published on 7/27/21 1:58 PM

Bulgaria's Agriculture Ministry reports increased harvest yields in 2021

The average wheat yields in Bulgaria are 55% higher than last year, the Ministry of Agriculture has announced . Grain growers also report that the harvest is successful and the harvest is good.  Unlike 2020, which the drought turned into the worst..

published on 7/27/21 9:55 AM