After Unit 6 of the Kozloduy Nuclear Power Plant was put into operation, a leak was ascertained in the coolant system of the electricity generator. Tests are being conducted to identify the cause of the problem, Minister of Energy in the caretaker government Rossen Hristov said for bTV.
“Until the leak is eliminated, the unit will remain disconnected from the national electric energy grid. There is no change in radiation levels. The problem is technical and it is in the non-nuclear part of the system. The reactor is in normal mode,” Minister Hristov said, and added that he hoped the deadline for completing the scheduled annual maintenance – 3 November - will be met.
The planned annual maintenance of Unit 6 of Bulgaria's only NPP, Kozloduy, has been completed. The unit was connected to the national grid at 10:07 following an inspection by the Nuclear Regulatory Agency. In addition to the repairs made to improve..
A quadripartite meeting of the interior ministers of Bulgaria, Hungary, Austria and Romania in Budapest on 22 November made it clear that Austria would lift its veto and that Bulgaria and Romania would probably become full members of Schengen from the..
President Rumen Radev met with Bulgarians living and working in Singapore during his visit to the Asian country on November 22-24. There are an estimated 400 Bulgarians living in Singapore. "Our diaspora in Singapore occupies a very special..
“It’s time to lift internal border controls now,” European Commissioner for Home Affairs Ylva Johansson believes. In an interview with RFE/RL she..
The Constitutional Court has opened a case following the request by President Rumen Radev for the amendments to the Constitution, endorsed by the 49 th..
Romania and Bulgaria have a chance to join the Schengen area by land as of January 2025 , Hungarian Interior Minister Sándor Pinter said after an..
+359 2 9336 661